PROJECT DETAILS
RTC Project No. 212068

RTC Project Manager (PM)
Scott Gibson, P.E.
(775) 335-1874
sgibson@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:
Wood Rodgers, Inc.

Construction Contractor: Granite Construction

PROJECT DESCRIPTION
The Sparks Consolidated 21-01 project consists of the scoping, design, and rehabilitation of Packer Way from Glendale Avenue to the cul-de-sac and Wild Island Court from Lincoln Way to the cul-de-sac in the City of Sparks.

LATEST NEWS
The project is complete.

SCHEDULE
Planning: Complete
Environmental: N\A
Preliminary Design: April to July 2020.
Final Design: January 2020
Construction: April 2021

FINANCIAL INFORMATION
Total Project Estimate: $1,750,000
Funding Source: RTC Fuel Tax

 

Post updated on: July 29, 2021