South Virginia Street And I-580 Exit 29 Capacity And Safety

PROJECT DETAILS


RTC Project No. 0217002

RTC Project Manager (PM)


Maria Paz Fernandez, P.E.


(775) 335-1861


mpazfernandez@rtcwashoe.com

RTC Engineering Department


(775) 348-0171

Design Firm: Wood Rodgers, Inc.

Construction Contractor: To be determined

PROJECT DESCRIPTION


Improve capacity and safety by widening South Virginia Street from the I-580 off ramp to Longley Lane.

LATEST NEWS


The team is coordinating with utilities, setting up Right of Way and finalizing access management mitigation treatments along with NDOT permit. Advertise for bid tentatively scheduled for early November 2023. Construction tentatively scheduled to start in the spring 2024.

May 2023 90% Design Virtual Public Meeting (Video)


SCHEDULE


Planning: Summer 2021


Environmental: N/A


Preliminary Design: End of 2022


Final Design: Fall 2023


Construction: Summer 2024

FINANCIAL INFORMATION


Total Project Estimate: $9,045,024


Funding Source: RTC Fuel Tax

Post updated on: September 29, 2023

South Virginia Street and I-580 Exit 29 Capacity and Safety Project Map