South Meadows Traffic Enhancements

PROJECT DETAILS


RTC Project No. 0217003

RTC Project Manager (PM)


Sara Going, P.E.


(775) 332-2143


sgoing@rtcwashoe.com

RTC Engineering Department


(775) 348-0171

Design Firm: Wood Rodgers, Inc.

Construction Contractor: To be determined

PROJECT DESCRIPTION 


The project will complete a selection of traffic enhancements as scoped in the South Meadows Parkway Multimodal Transportation Study:

  • Extension of the eastbound to northbound left turn pocket at South Meadows Parkway and Gateway Drive
  • Closing the north side sidewalk gap on South Meadows Parkway between Evergreen Street and Double Diamond Parkway
  • South Meadows Parkway fiber optic connection from Double R Boulevard to Veterans Parkway
  • Lane balance restripe on eastbound Damonte Ranch Parkway approaching the I-580 northbound on-ramp
  • Add westbound to northbound right turn pocket at Damonte Ranch Parkway and Double R Boulevard

The project will also complete Intersection Control Evaluations for:

  • South Virginia Street and Holcomb Ranch Lane
  • Rio Wrangler Parkway and McCauley Ranch Boulevard

LATEST NEWS


The project is scheduled to advertise for construction bids in Fall 2023.

SCHEDULE


Planning: N/A


Environmental: N/A


Preliminary Design: Fall 2022


Final Design: Summer 2023


Construction: Spring 2024

FINANCIAL INFORMATION


Total Project Estimate: $ 4,090,000.00


Funding Source: RTC Fuel Tax

Post updated on: September 29, 2023

South Meadows Traffic Enhancements Map