PROJECT DETAILS
RTC Project No. 512017

RTC Project Manager (PM)
Blaine Petersen, P.E.
775-335-1871
bpetersen@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:
Atkins North America

Construction Contractor: To be determined

PROJECT DESCRIPTION
Widening from one lane in each direction to two lanes in each direction with a center turn lane and rehabilitation of Sky Vista Parkway from Silver Lake Drive to just east of Sky Vista Parkway. Improvements include street lighting, eight-foot sidewalks and five-foot bike lanes on both sides of the roadway.

LATEST NEWS
Project is currently in final design phase.

SCHEDULE
Planning: Winter 2018-2019
Environmental: N/A
Preliminary Design: February 2020 to October 2020
Final Design: March 2022
Construction: Spring 2022

FINANCIAL INFORMATION
Total Project Estimate: $15,800,000
Funding Source: Regional Road Impact Fee (RRIF)

 

Post updated on: July 29, 2021