PROJECT DETAILS
RTC Project No. 512017

RTC Project Manager (PM)
Warren Call, P.E.
775-335-1881
Wcall@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:
Atkins North America

Construction Contractor: to be determined

PROJECT DESCRIPTION
Widening from one way in each direction to two lanes in each direction with a center turn lane and rehabilitation of Sky Vista Parkway from Silver Lake Drive to just east of Sky Vista Parkway. Project will include street lighting, sidewalks and five bike lanes on both sides of the roadway.

LATEST NEWS
Currently under preliminary design. Geotechnical Exploration is complete.

Schedule
Planning: Winter 2018-2019
Environmental: N\A
Preliminary Design: Summer 2020
Final Design: 2020
Construction: 2022

FINANCIAL INFORMATION
Total Project Estimate: $15,270,735
Amount Approved: $2,709,038
Funding Source: RTC Fuel Tax

Post updated on: June 29, 2020