Selmi Drive Rehabilitation

PROJECT DETAILS


RTC Project No. 0212077

RTC Project Manager (PM)


Maria Paz Fernandez, P.E.


(775) 335-1861


mpazfernandez@rtcwashoe.com

RTC Engineering Department


(775) 348-0171

Design Firm: Farr West Engineering

Construction Contractor: To be determined

PROJECT DESCRIPTION


This is a project selected from the Rehabilitation and Reconstruction Program for construction on 2024. Pavement reconstruction on Selmi Drive from Sutro Street to Clear Acre Lane.

LATEST NEWS


Design is underway and Ninety percent plans were submitted to the City of Reno for comments on August 31, 2023. Construction is expected to start in Spring 2024.

SCHEDULE


Planning: N/A


Environmental: N/A


Preliminary Design: Summer 2023


Final Design: Winter 2023


Construction: Spring 2024

FINANCIAL INFORMATION


Total Project Estimate: $1,950,000


Funding Source: RTC Fuel Tax

Post updated on: September 29, 2023

Selmi Drive Rehabilitation Project Map