PROJECT DETAILS
RTC Project No. 212072

RTC Project Manager (PM)
Maria Paz Fernandez, P.E.
(775) 335-1861
mpazfernandez@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: CA Group

Construction Contractor: To be determined

PROJECT DESCRIPTION
The project includes rehabilitation and reconstruction of the pavement roadway on Sutro Street from 9th Street to Oddie Boulevard and on Enterprise Road from Evans Avenue to Valley Road. The majority of the construction work will be limited to the pavement including striping since there are existing ADA compliant sidewalks throughout the project limits.

LATEST NEWS
Currently in process of procuring design services.  Preliminary design is estimated to begin in September 2021.

SCHEDULE
Planning: Complete July 2021
Environmental: N/A
Preliminary Design: September 2021 to March 2022
Final Design: Spring 2022
Construction: Summer 2022

FINANCIAL INFORMATION
Total Project Estimate: $2,500,000.00
Funding Source: RTC Fuel Tax

 

Post updated on: August 30, 2021