PROJECT DETAILS
RTC Project No. 0212069

RTC Project Manager (PM)
Scott Gibson, P.E.
(775) 335-1874
sgibson@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Eastern Sierra Engineering, P.C

Construction Contractor: Granite Construction Company

PROJECT DESCRIPTION
Roadway reconstruction of Sky Valley Drive from Summit Ridge Drive to the Highland Ditch Crossing and Sky Mountain Drive from the Highland Ditch crossing to Summit Ridge Drive

Construction will include removal and replacement of the roadway structural section, sidewalk and curb and gutter replacement as necessary, correction of  localized drainage deficiencies, reconstruction of existing curb ramps, bus stop improvements, and other incidentals necessary for the reconstruction of the street segments within the Project limits.

LATEST NEWS
Construction is in progress. Paving of the counterclockwise roadway has been completed and traffic will switch to the inside and move counter clockwise starting June 2, 2022. Concrete work is nearly complete with paving scheduled for early July 2022 and completion in mid July 2022.

For current traffic control information please visit https://www.rtcwashoe.com/engineering-construction/ and click on Weekly Traffic Control Report.

VIDEO:

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Completed
Final Design: Completed
Construction: April – July 2022

FINANCIAL INFORMATION
Total Project Estimate: $3,869,455
Funding Source: RTC Fuel Tax

 

Post updated on: June 30, 2022