PROJECT DESCRIPTION
Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk and curb and gutter replacement as necessary. Correction of localized drainage deficiencies, reconstruction of existing curb ramps, reconstruction of driveways, and other incidentals necessary for the rehabilitation and/or reconstruction of the street segments within the Project limits.

Rehabilitation and/or reconstruction of the following streets:
• Armstrong Lane from Susileen Drive to Yuma Lane
• Yuma Lane from Armstrong Lane to Hunter Lake Drive
• Lune Lane from Wedekind Road to Northetowne Lane

The Reno Consolidated 21-01 Project is part of the approved 2021 Roadway Reconstruction Projects.

LATEST NEWS

Project is under 90% design development. 90% plans should be ready by mid-October.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: April – June 2020
Final Design: July – December 2020
Construction: Spring 2021

FINANCIAL INFORMATION
Total Project Estimate: $2,500,000
Funding Source: RTC Fuel Tax

 