PROJECT DETAILS
RTC Project No. 212065

RTC Project Manager (PM)
Dale Keller, P.E.
(775) 335-1827
dkeller@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Eastern Sierra Engineering (ESE)

Construction Contractor: to be determined

PROJECT DESCRIPTION
Rehabilitation and/or reconstruction of the following streets:
• Armstrong Lane from Susileen Dr to Yuma Ln
• Yuma Lane from Armstrong Ln to Hunter Lake Dr
• Lune Lane from Wedekind Rd to Northetowne Ln

Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk and curb and gutter replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing curb ramps, reconstruction of driveways, and other incidentals necessary for the rehabilitation and/or reconstruction of the street segments within the Project limits.

LATEST NEWS
The preliminary design submittal is under agency review.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: April – June 2020
Final Design: July – December 2020
Construction: Spring 2021

FINANCIAL INFORMATION
Total Project Estimate: $2,500,000
Amount Approved: $2,500,000
Funding Source: RTC Fuel Tax

[The Reno Consolidated 21-01 Project is part of the approved 2021 Roadway Reconstruction Projects.]

Post updated on: June 29, 2020