PROJECT DETAILS
RTC Project No. 212064

RTC Project Manager (PM)
Judy Tortelli, P.E.
(775) 335-1824
jtortelli@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Nichols Consulting Engineers

Construction Contractor: To be determined

PROJECT DESCRIPTION
Rehabilitation and/or reconstruction of the following streets:

  • Mayberry Drive from Memory Lane to California Avenue
  • California Avenue from Hunter Lake Drive to Booth Street
  • First Street from Sierra Street to Virginia Street

Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk and curb and gutter replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing curb ramps, reconstruction of driveways, and other incidentals necessary for the rehabilitation and/or reconstruction of the street segments within the Project limits.

May 27 to June 30, 2020

Virtual Project Presentation

Presentation (pdf format)

***Comment Form*** please submit comments by June 30, 2020

Notice

Post Card

FAQs First Street

FAQs Mayberry Drive

Vicinity Map

Cross Sections

Conceptual Design – California Avenue & Mayberry Drive Intersection

Conceptual Design – California Avenue from Hunter Lake Drive to Booth Street

***Comment Matrix*** (coming in July 2020)

LATEST NEWS
A Virtual Project Presentation to inform the public of the status of the Project will be posted on the website soon. The improvements on First Street from Sierra Street to Virginia Street have been pulled from the project due to potential increased improvements. The City is considering adding full traffic signal replacement at the  Sierra/First Street intersection. The Project Team is preparing bidding documents.  Construction has been delayed and is anticipated to start in Spring 2022.

SCHEDULE
Planning: September 2019 – January 2020
Environmental: N/A
Preliminary Design: January – March 2020
Final Design: April 2020 – July 2021
Construction: Spring 2022

FINANCIAL INFORMATION
Total Project Estimate: $4,610,000
Funding Source: RTC Fuel Tax

 

Post updated on: September 30, 2021