PROJECT DETAILS
RTC Project No. 212059

RTC Project Manager (PM)
Maria Paz Fernandez, P.E.
(775) 335-1861
mpazfernandez@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  Wood Rodgers, Inc.

Construction Contractor:  to be determined

PROJECT DESCRIPTION
Rehabilitation and/or reconstruction of the following streets:
• North Hills Boulevard from Lemmon Drive to Golden Valley Road;
• Hunter Lake Drive and Foster Drive intersection; and,
• Sky Vista Parkway from Lemmon Drive to Silver Lake Road.

Construction work will include removal and replacement of the roadway structural section, mill and fill, roadway surface treatment, sidewalk, curb and replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing handicapped ramps, reconstruction of driveways, and other incidentals necessary for the rehabilitation of and/or reconstruction of the street segments within the Project limits.

LATEST NEWS
The Invitation for Bids for project construction advertised on June 10, 2019, with the Bid Opening scheduled for July 1, 2019. Construction is expected to begin by the end of July 2019.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: June 2019
Construction: to be determined

FINANCIAL INFORMATION
Total Project Estimate: $3.5 Million
Amount Approved: Pending Interlocal Cooperative Agreement
Funding Source: RTC Fuel Tax

Post updated on: June 25, 2019