PROJECT DETAILS
RTC Project No. 212058

RTC Project Manager (PM)
Judy Tortelli, P.E.,
(775) 335-1824
jtortelli@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  CA Group

Construction Contractor: Sierra Nevada Construction, Inc.

PROJECT DESCRIPTION
Rehabilitation and/or reconstruction the following streets:
• Sutro Street from the Truckee River Bridge to 4th Street
• Sutro Street from McCarran Boulevard to the northern edge
• 1st Street from Center Street to Lake Street
• Lake Street bridge over the Truckee River
• State Street from Virginia Street to Sinclair Street

Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk, curb and replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing handicapped ramps, reconstruction of driveways, traffic signal improvements at the Sutro/McCarran and 1st/Lake intersections, and other incidentals necessary for the rehabilitation and/or reconstruction of the street segments within the Project limits.

LATEST NEWS
The Construction Contract was awarded to Sierra Nevada Construction, Inc. (SNC), on July 19, 2019. Construction is expected to begin August 12, 2019.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Complete
Final Design:  Complete
Construction: August 2019 to December 2019

FINANCIAL INFORMATION
Total Project Estimate: $2.4 Million
Amount Approved:  $4.2 Million
Funding Source: RTC Fuel Tax

Currently, the project is approved for design and engineering during construction services.

Post updated on: August 29, 2019