PROJECT DETAILS
RTC Project No. 212058

RTC Project Manager (PM)
Judy Tortelli, P.E.,
(775) 335-1824
jtortelli@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  CA Group

Construction Contractor: Sierra Nevada Construction, Inc.

PROJECT DESCRIPTION
Rehabilitation and/or reconstruction the following streets:
• Sutro Street from the Truckee River Bridge to 4th Street
• Sutro Street from McCarran Boulevard to the northern edge
• 1st Street from Center Street to Lake Street
• Lake Street bridge over the Truckee River
• State Street from Virginia Street to Sinclair Street

Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk, curb and replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing handicapped ramps, reconstruction of driveways, traffic signal improvements at the Sutro/McCarran and 1st/Lake intersections, and other incidentals necessary for the rehabilitation and/or reconstruction of the street segments within the Project limits.

LATEST NEWS
Construction of State Street, First Street and Lake Street is complete.

Work on Sutro Street from Selmi Drive to the northern edge is complete.

Work on Sutro Street from McCarran Boulveard to Selmi Drive has been delayed to Spring, 2020.

Work on Sutro Street from the Truckee River Bridge to 4th Street is complete.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Complete
Final Design:  Complete
Construction: August 2019 to May 2020

FINANCIAL INFORMATION
Total Project Estimate: $4,300,232
Amount Approved: $4,291,000
Funding Source: RTC Fuel Tax

Currently, the project is approved for design and engineering during construction services.

Post updated on: November 22, 2019