PROJECT DETAILS
RTC Project No. 212064

RTC Project Manager (PM)
Judy Tortelli, P.E.
(775) 335-1824
jtortelli@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: NCE

Construction Contractor: to be determined

PROJECT DESCRIPTION
Rehabilitation and/or reconstruction of the following streets:

  • Mayberry Drive from Memory Ln to California Ave
  • California Avenue from Hunter Lake Dr to Booth St
  • First Street from Sierra St to Virginia St

Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk and curb and gutter replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing curb ramps, reconstruction of driveways, and other incidentals necessary for the rehabilitation and/or reconstruction of the street segments within the Project limits.

May 27 to June 30, 2020

Virtual Project Presentation

Presentation (pdf format)

***Comment Form*** please submit comments by June 30, 2020

Notice

Post Card

FAQs First Street

FAQs Mayberry Drive

Vicinity Map

Cross Sections

Conceptual Design – California Avenue & Mayberry Drive Intersection

Conceptual Design – California Avenue from Hunter Lake Drive to Booth Street

***Comment Matrix*** (coming in July 2020)

LATEST NEWS
The NCE design team is working through preliminary design of the project.  Horizontal layout, grading, roadway rehabilitation options, and identifying utility conflicts is ongoing.  A 30% Design Review meeting was held on April 1, 2020, and the preferred conceptual alternative at the Mayberry/California intersection has been determined.

Due to the COVID-19 social distancing restrictions, we are unable to hold an in-person public informational meeting.  In its place, we are providing a Virtual Project Presentation where the public can learn about the project and submit questions and comments.

SCHEDULE
Planning: September 2019 – January 2020
Environmental: N/A
Preliminary Design: January – March 2020
Final Design: April – December 2020
Construction: Summer 2021

FINANCIAL INFORMATION
Total Project Estimate: $4,400,000
Amount Approved: $1,000,000
Funding Source: RTC Fuel Tax

 

Post updated on: June 29, 2020