PROJECT DESCRIPTION
Pyramid Highway Operations Improvements:
- Ingenuity Avenue to Egyptian Drive
LATEST NEWS
RTC is currently negotiating scope/fee with a consultant for preliminary design efforts for the project. A contract for engineering services is anticipated on the Fall RTC Board meeting agenda.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring/Summer 2024
Final Design: Summer 2025
Construction: Summer/Fall 2025
FINANCIAL INFORMATION
Total Project Estimate: 15,200,000
Funding Source: RTC Fuel Tax