PROJECT DETAILS
RTC Project No. 222028

RTC Project Manager (PM)
Judy Tortelli, P.E.
(775) 335-1824
jtortelli@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Stantec Consulting Services, Inc.

Construction Contractor: Spanish Springs Construction, Inc,

PROJECT DESCRIPTION
Rehabilitation and/or reconstruction of Prater Way from Howard Drive to Sparks Blvd.  Construction work may include removal and replacement of the roadway structural section, mill and fill, sidewalk and curb and gutter replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing curb ramps, reconstruction of driveways, replacement of sanitary sewer infrastructure, and other incidentals necessary for the rehabilitation and/or reconstruction of the street within the Project limits.

A Fact Sheet, Map of the Project area, and other information are available for download below:
Map
Fact Sheet
Clear Zone Evaluation

Thursday, January 9, 2020 Public Kick-off Meeting
Notice
Presentation
Display Boards

LATEST NEWS
Spanish Springs Construction has completed all underground work on E. Prater Way. Approximately 2,000 lineal feet of sewer, 15,000 square feet of sidewalk, and 3,000 lineal feet of curb and gutter have been replaced. In addition almost one mile of new conduit has been installed for Sparks Police Department Communications. All concrete work and the bottom section of roadway pavement has been completed on the north side of the roadway. Traffic has been switched to the north side of E. Prater Way so work on the south side can begin. Construction of the Project is anticipated to be complete by early October.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: August – November 2019
Final Design: December – February 2020
Construction: April – October 2020

FINANCIAL INFORMATION
Total Project Estimate: $5,000,000
Funding Source: RTC Fuel Tax

 

Post updated on:  August 31, 2020