The project is at Virginia Line RAPID station at Peppermill northbound.

LATEST NEWS
The project reached substantial completion and the bus stop is operational.

SCHEDULE
Planning: 2020
Environmental: 2020
Preliminary Design: 2021
Final Design: 2022
Construction: 2023

FINANCIAL INFORMATION
Total Project Estimate: $3,246,000
Funding Source: RTC Fuel Tax