PROJECT DETAILS
RTC Project No. 512013

RTC Project Manager (PM)
Maria Paz Fernandez, P.E.
(775) 335-1861
mpazfernandez@rtcwashoe.com

Design Firm: Stantec Consulting, Inc.

Construction Contractor: Granite Construction Company, Nichols Consulting Engineers (NCE)

PROJECT DESCRIPTION
This project consists of studying and developing alternatives for the Oddie/Wells Corridor based on the findings shown in the Corridor Study performed and approved in 2013 by the RTC. This is a Complete Streets project that includes safety improvements to several modes of transportation such as sidewalks, bike lanes, comfortable and accessible public transportation stops, frequent and safe crossing opportunities, median islands, accessible pedestrian signals, curb extensions, narrower travel lanes, and more.

LATEST NEWS
Construction on Phase 1 of the project is in progress on Oddie Boulevard from Pyramid Way to Sullivan Lane.  For current traffic control information, please visit https://www.rtcwashoe.com/engineering-construction/ and click on Weekly Traffic Control Report.

  • Roadwork began March 21, 2022 and will continue for approximately six months (September 2022).
  • Privacy wall construction began March 18, 2022. Residents affected by construction were notified.

Visit http://oddiewellsproject.com/ for more information about the project, to provide comments and to sign up for updates.

SCHEDULE
Planning: Complete 2013
Environmental: N/A
Preliminary Design: Fall 2019
Final Design: Winter 2020
Construction: Fall 2021

FINANCIAL INFORMATION
Total Project Estimate: $51,629,070
Funding Source: RTC Fuel Tax

 

Post updated on: June 29, 2022

Oddie/Wells Corridor Multi-Modal Improvements Project Map