PROJECT DETAILS
RTC Project No. 0212078

RTC Project Manager (PM)
Amanda Callegari, P.E.
(775) 335-1881
acallegari@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Nichols Consulting Engineers, CHTD

Construction Contractor: To be determined

PROJECT DESCRIPTION

Part of RTC’s Pavement Preservation Program, this Project will reconstruct the pavement on North Virginia Street from the Lawlor roundabout to North McCarran Boulevard. Anticipated improvements include roadway reconstruction, bike lanes, and other roadway appurtenances as deemed necessary, such as portions of sidewalk, curb and gutter, and median.

LATEST NEWS

Preliminary design for this project will kick-off in December 2022.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: January 2023 – March 2023
Final Design: March 2023 – August 2023
Construction: May 2024

FINANCIAL INFORMATION
Total Project Estimate: $2,900,000
Funding Source: RTC Fuel Tax

 

Post updated on: November 29, 2022

North Virginia Street University Rehabilitation Project Map