PROJECT DETAILS
RTC Project No. 212066

RTC Project Manager (PM)
Roy Flores, P.E., M.P.A.
(775) 335-1881
rflores@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: CA Group, Inc.

Construction Contractor: Sierra Nevada Construction, Inc.

PROJECT DESCRIPTION
Roadway rehabilitation of Newport Lane from Link Lane to McDaniel Street . The Project will consist of roadway removal and reconstruct; improve existing S/W and D/W and new sidewalk; ADA improvements and striping; and install new storm drain. No bike lanes.

LATEST NEWS
Project is under construction and will finish by the end of October 2021.

SCHEDULE
Planning: Completed
Environmental: N/A
Preliminary Design: Completed
Final Design: Completed
Construction: August 2021 to October 2021

FINANCIAL INFORMATION
Total Project Estimate: $2,000,000
Funding Source: RTC Fuel Tax

 

Post updated on: September 30, 2021