PROJECT DETAILS
RTC Project No. 0212069

RTC Project Manager (PM)
Roy Flores, P.E., M.P.A.
(775) 335-1881
rflores@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Eastern Sierra Engineering, P.C

Construction Contractor: To Be Determined

PROJECT DESCRIPTION
Construction work may include removal and replacement of the roadway structural section, sidewalk and curb and gutter replacement as necessary, correction of localized drainage deficiencies, reconstruction of existing curb ramps, bus stop improvements, and other incidentals necessary for the rehabilitation and/or
reconstruction of the street segments within the Project limits.

Rehabilitation and/or reconstruction of the following streets:
Sky Valley Drive from Summit Ridge Drive to the Highland Ditch Crossing
Sky Mountain Drive from the Highland Ditch crossing to Summit Ridge Drive

LATEST NEWS
Eastern Sierra Engineering was selected from the Engineering Design and Construction Management shortlist to perform design and engineering during construction services for the Project. The design team submitted 50% Design Plans for agency review in March. The Project is anticipated to go to construction
early next year.

SCHEDULE
Planning: Completed
Environmental: N/A
Preliminary Design: November 2020 – March 2021
Final Design: March – September 2021
Construction: April – July 2022

FINANCIAL INFORMATION
Total Project Estimate: $4,700,000
Funding Source: RTC Fuel Tax

 

Post updated on: March 31, 2021