PROJECT DETAILS
RTC Project No. 215005

RTC Project Manager (PM)
Scott Gibson, P.E.
(775) 335-1874
sgibson@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Poggemeyer Design Group

Construction Contractor:  Spanish Springs Construction

PROJECT DESCRIPTION
Develop various complete street improvements along Mill Street from 1-580 to McCarran Boulevard, as identified in the RTC Complete Streets Masterplan completed in July 2016 and the Mill Terminal Corridor Study completed in March 2013. Although this roadway segment has had some existing complete street treatments, more improvements have been identified to conform to the RTC masterplan. The emphasis of this project is to assess and identify improvements for pedestrians, bicyclists, and transit riders as well as motorists. Deficiencies in pedestrian access related to Charter Schools and AACT High School in the area as well as a number of ADA deficient bus stops have been identified.

LATEST NEWS
Bids were opened for the project on November 16, 2021, and the project has been awarded to Spanish Springs Construction. Construction has begun and the contractor is working on the north side of Mill Street from McCarran Boulevard to Terminal Way. The outside west bound lanes are closed to accommodate construction and traffic is one lane westbound.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: N/A
Final Design: June 2020
Construction: February 2022 – July 2022

FINANCIAL INFORMATION
Total Project Estimate: $5,550,000
Funding Source: RTC Fuel Tax

 

Post updated on: June 30, 2022

Mill Street Complete Street Project Map