PROJECT DETAILS
RTC Project No. 211007

RTC Project Manager (PM)
Kimberly Diegle, P.E.
(775) 335-1884
kdiegle@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Jacobs Engineering Group

Construction Contractor: To be determined

PROJECT DESCRIPTION
The Mill Street Capacity and Safety project limits are from Kietzke Lane to Terminal Way, approximately 0.75 miles in total length. Proposed improvements include widening Mill Street from Kietzke Lane to the I-580 southbound on-ramp from four to five lanes.  Proposed improvements on Mill Street from the I-580 northbound on-ramp Interchange to Terminal Way include a raised median and will maintain the existing four travel lanes.  The project improvements also exclude the I-580 interchange which was recently improved with NDOT’s Spaghetti Bowl Xpress (SBX) project.

LATEST NEWS
The RTC is reviewing input received during the public comment period as preliminary design progresses for Mill Street improvements. Please visit www.millstreetwidening.com for additional information.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring 2022 – Fall 2022
Final Design: Winter 2023 – Spring 2024
Construction: Summer 2024

FINANCIAL INFORMATION
Total Project Estimate: $60,000,000
Funding Source: RTC Fuel Tax

 

Post updated on: September 29, 2022

Mill Street Capacity and Safety Project Map