PROJECT DETAILS
RTC Project No. 0227003

RTC Project Manager (PM)
Alex Wolfson, P.E., PTOE, RSP1
(775)335-1880
awolfson@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Design Firm: HDR

Construction Contractor: Quanta Telecommunication Services

PROJECT DESCRIPTION
This project is to connect some of the traffic signals with fiber to improve traffic signal operations and safety on the following corridors:

  • Pyramid Way between Nugget Avenue and C Street and Victorian Avenue/I-80
  • North McCarran Boulevard between Rock Boulevard and Sullivan Lane

LATEST NEWS
Construction is expected to begin in September 2023.

SCHEDULE
Planning: NA
Environmental: N/A
Preliminary Design: Current to November 2022
Final Design: November 2022 to May 2023
Construction: September 2023 – Winter 2024

FINANCIAL INFORMATION
Total Project Estimate:
$1,589,643.25
Funding Source: RTC Fuel Tax


Post updated on: August 25, 2023

N McCarran Boulevard & Pyramid Highway Fiber Project Map