PROJECT DETAILS
RTC Project No. 0227003

RTC Project Manager (PM)
Alex Wolfson, P.E.
(775)335-1880
awolfson@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Design Firm: HDR

Construction Contractor: To be determined

PROJECT DESCRIPTION
This project is to connect some of the traffic signals with fiber around the City of Sparks to help improve traffic operations. The target intersections are:

  • North McCarran Boulevard at Sullivan Lane
  • Pyramid Way at C Street and Victorian Avenue/I-80

LATEST NEWS
Project is under design with construction expected to start in late spring 2023.

SCHEDULE
Planning: NA
Environmental: N/A
Preliminary Design: Current to November 2022
Final Design: November 2022 to February 2023
Construction: Summer 2023

FINANCIAL INFORMATION
Total Project Estimate:
$1,750,000
Funding Source: RTC Fuel Tax


Post updated on: March 31, 2023

N McCarran Boulevard & Pyramid Highway Fiber Project Map