PROJECT DETAILS
RTC Project No. 0217001

RTC Project Manager (PM)
Bryan Byrne
(775) 335-1865
bbyrne@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Preliminary Design Firm: CA Group, Inc.

NEPA/Final Design Firm: To be determined

Construction Contractor: To be determined

PROJECT DESCRIPTION
The project includes operational improvements along Lemmon Drive from Fleetwood Drive to Ramsey Way. Elements of this project include resilience improvements to mitigate historical flooding issues.

LATEST NEWS
RTC completed an Alternatives Analysis Report for Segment 2 of the Lemmon Drive Roadway Project in August of 2022. After selecting the Natural Berm Alternative the project team completed preliminary design (30 percent design) in October of 2022. The RTC has procured a consultant designer to progress design and complete the NEPA environmental process.

Lemmon Drive Segment 2 – Alternatives (Level 1)

Lemmon Drive Segment 2 – Alternatives (Level 2)

Lemmon Drive Segment 2 – 30% Preliminary Plans

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: 2020-2022
Final Design: 2023-2024
Construction: To be determined (based on funding)

FINANCIAL INFORMATION
Total Project Estimate: $49,200,000.00
Funding Source: RTC Fuel Tax

 

Post updated on: August 28, 2023

Lemmon Drive Segment 2 Traffic Improvements and Resiliency Project Map