PROJECT DETAILS
RTC Project No. 247006

RTC Project Manager (PM)
Dale Keller, P.E.
(775) 335-1827
dkeller@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Jacobs Engineering Group

Construction Contractor: To be determined

PROJECT DESCRIPTION
The project includes widening Lemmon Drive from US 395 to Military Road from four lanes to six lanes and reconstructing the US 395 / Lemmon Drive interchange (Segment #01) and widening Lemmon Drive from Fleetwood Drive to Chickadee Drive from two lanes to four lanes (Segment #02).

LATEST NEWS
The final design of Segment 1 has been reviewed by the RTC, NDOT, and City of Reno. Theconstruction bid date is anticipated to be in April 2021 with construction beginning in June 2021.

The project team continues the Level 2 screening process for the top three (3) alternatives. The Top 3 Alternatives were presented to the RTC Board at the August 20, 2020 meeting. The Level 2 screening process includes a qualitative evaluation where the top alternatives are screen on the criteria developed and agreed upon the Technical Advisory Committee (TAC).

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: October 2019 – July 2020
Final Design: August 2020 – January 2021 (Segment #01 only)
Construction: Spring 2021 – Summer 2022

FINANCIAL INFORMATION
Total Project Estimate: $22,500,000
Funding Source: RTC Fuel Tax

 

Post updated on: March 31, 2021