PROJECT DETAILS
RTC Project No. 0217001

RTC Project Manager (PM)
Dale Keller, P.E.
(775) 335-1827
dkeller@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Jacobs Engineering Group

Construction Contractor: To be determined

PROJECT DESCRIPTION
The project includes operational improvements along Lemmon Drive from Fleetwood Drive to Ramsey Way.

LATEST NEWS
The project team continues to refine the top three roadway alternatives for additional input. The project team is working with Washoe County on hydraulic modeling of the basin.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: 2020-Winter 2021
Final Design: 2023-2024
Construction: To be determined based on funding

FINANCIAL INFORMATION
Total Project Estimate: $39,000,000.00
Funding Source: RTC Fuel Tax

 

Post updated on: July 29, 2021