PROJECT DESCRIPTION
The project includes widening Lemmon Drive from US 395 to Military Road from four lanes to six lanes (Segment #01) and widening Lemmon Drive from Fleetwood Drive to Chickadee Drive from two lanes to four lanes (Segment #02).
LATEST NEWS
The final design of Segment 1 is underway. The 90% plans and specifications are under agency review. The US 395/Lemmon Drive interchange design continues to progress. The anticipated construction start date is spring 2021.
The project team continues the Level 2 screening process for the top three (3) alternatives. The Top 3 Alternatives were presented to the RTC Board at the August 20, 2020 meeting. The Level 2 screening process includes a qualitative evaluation where the top alternatives are screen on the criteria developed and agreed upon the Technical Advisory Committee (TAC).
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: October 2019 – July 2020
Final Design: August 2020 – January 2021 (Segment #01 only)
Construction: Spring 2021 – Summer 2022
FINANCIAL INFORMATION
Total Project Estimate: $22,500,000
Funding Source: RTC Fuel Tax
Post updated on: December 28, 2020