PROJECT DETAILS
RTC Project No. 212062

RTC Project Manager (PM)
Warren Call, P.E.
(775) 335-1881
wcall@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Eastern Sierra Engineering

Construction Contractor: Sierra Nevada Construction (SNC)

PROJECT DESCRIPTION
The project limits are from Evans Creek Drive north to McCarran Boulevard.  Construction will consist of roadway reconstruction, curb/gutter and sidewalk repairs, ADA compliant driveway access, re-stripe roadway for parking and bike lanes on both sides of the roadway, and pedestrian crossing signage.

A map of the Project area and other information is available for download below:
Project Area Map
Map Figure presented at public meeting

LATEST NEWS
Please exercise caution through the work zone. Project completion is scheduled for the end of September 2020.

SCHEDULE
Planning: Completed
Environmental: N/A
Preliminary Design: Completed
Final Design: December 2019 to March 2020
Construction: July 20, 2020 to September 28, 2020

FINANCIAL INFORMATION
Total Project Estimate: $2,182,267.00
Funding Source: RTC Fuel Tax

Post updated on: September 28, 2020