PROJECT DETAILS
RTC Project No. 0212070

RTC Project Manager (PM)
Jeff Wilbrecht, P.E.
(775) 335-1872
jwilbrecht@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Lumos & Associates

Construction Contractor: To be determined

PROJECT DESCRIPTION
Roadway rehabilitation between Wyoming Avenue and North McCarran Boulevard.  The project will include some sidewalk replacement, restriping of lanes, addition of uphill bike lane, and minor utility work.

LATEST NEWS
Project design is complete.  Currently advertising for construction services, bid submittal required by January 18, 2022.

SCHEDULE
Planning: Spring/Summer 2020
Environmental: N/A
Preliminary Design: Winter 2020/Spring 2021
Final Design: 2021
Construction: 2022

FINANCIAL INFORMATION
Total Project Estimate: $3,815,000
Funding Source: RTC Fuel Tax

 

Post updated on: December 31, 2021

Kings Row Rehabilitation Project Phase 2 (Wyoming Avenue to McCarran Boulevard)