Status: Upcoming Projects
Total Project Cost: $1,053,000
PROJECT DETAILS
RTC Project No. 0217008
RTC Project Manager (PM)
Garrett Rodgers, P.E.
(775) 332-2139
grodgers@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: Kimley-Horn and Associates
Construction Contractor: To be determined
PROJECT DESCRIPTION
Work includes installation of fiber optic communications for traffic signals on Kietzke Lane and Second Street in Reno.
LATEST NEWS
The project design is complete. A solicitation package is being prepared for project advertisement in March 2024.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Fall 2023
Final Design: Spring 2024
Construction: Spring 2024
FINANCIAL INFORMATION
Total Project Estimate: $1,053,000
Funding Source: RTC Fuel Tax
Post updated on: March 22, 2024
Kietzke Lane ITS Project Map