ITS Traffic Management Phase 4

PROJECT DETAILS
RTC Project No. 247009

RTC Project Manager (PM)
Alex Wolfson, P.E., PTOE, RSP1
(775) 335-1880
awolfson@rtcwashoe.com
RTC Engineering Department

(775) 348-0171

Design Firm:  Kimley-Horn and Associates

Construction Contractor:  Titan Electrical Contracting

PROJECT DESCRIPTION
Project will expand traffic communication network with fiber optics and will include other ITS infrastructure.  An update to the 2016 ITS Master Plan, investigation of Dynamic Message Signs (DMS) coordination and investigation of flow detection/traveler information infrastructure is included in the project.

LATEST NEWS
Construction is substantially complete. Final punch list items are being worked on including testing of new fiber infrastructure.

SCHEDULE
Planning:  Complete
Environmental:  N/A
Preliminary Design: Complete
Final Design:  Winter 2021
Construction:  Spring 2023

FINANCIAL INFORMATION
Total Project Estimate:$2,107,000
Funding Source:  RTC Fuel Tax

Post updated on: September 29, 2023

ITS Traffic Management Phase 4 Project Map