PROJECT DETAILS
RTC Project No. 247003

RTC Project Manager (PM)
Blaine Petersen, P.E.
(775) 335-1871
bpetersen@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  Kimley – Horn and Associates

Construction Contractor:  Titan Electrical Contracting

PROJECT DESCRIPTION
This project will expand communication to outlying signal systems and install ITS devices to monitor and remotely adjust traffic signals to respond to special events, changing traffic conditions, provide information to drivers or traffic incidents.

LATEST NEWS
Project is substantially complete.

SCHEDULE
Planning: Complete December 2014
Environmental: Complete August 2016
Preliminary Design: N/A
Final Design:  Complete January 2018
Construction:  June 2018 to September 2018

FINANCIAL INFORMATION
Total Project Estimate: $840,000
Amount Approved: $840,000
Funding Source: Fuel Tax

Post updated on:   November 21, 2018