PROJECT DETAILS
RTC Project No. 247008

RTC Project Manager (PM)
Blaine Petersen
(775) 335-1871
bpetersen@rtcwashoe.com

RTC Engineering Department

(775) 348-0171
(775) 348-0170 fax

Design Firm: to be determined

Construction Contractor: to be determined

PROJECT DESCRIPTION
Installation of fiber optic communication along Rock Blvd., Road Weather Information System (RWIS) in northwest Reno and installation of Performance Package to up to 20 Gridsmart cameras to allow detection of pedestrian and bicycles.

LATEST NEWS
Negotiating with design consultant for design and Engineering During Construction (EDC) contract. Anticipate design complete spring of 2020.

SCHEDULE
Preliminary Design: Winter 2019/2020
Final Design: Spring 2020
Construction: Summer/ Fall 2020

FINANCIAL INFORMATION
Total Project Estimate:$ 1,000,000
Amount Approved: $ 1,000,000
Funding Source: Regional Road Impact Fees (RRIF)

 

Post updated on:  November 22, 2019