PROJECT DETAILS
RTC Project No. 0212074

RTC Project Manager (PM)
Jeff Wilbrecht, P.E.
(775) 335-1872
jwilbrecht@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Wood Rodgers, Inc.

Construction Contractor: To be determined

PROJECT DESCRIPTION
Reconstruction of Holcomb Avenue from Burns Street to Liberty Street.  Work will primarily focus on reconstruction of the asphalt pavement roadway.  Additional work will include isolated concrete sidewalk, curb, gutter removal and replacement.

LATEST NEWS
The project is kicking off with preliminary investigations, preliminary design work is underway.

SCHEDULE
Planning: January 2021 to July 2021
Environmental: N/A
Preliminary Design: August 2021 to December 2021
Final Design: Spring and Summer 2022
Construction: Spring and Summer 2023

FINANCIAL INFORMATION
Total Project Estimate:
$3,531,000
Funding Source: RTC Fuel Tax

 

Post updated on: November 30, 2021

Holcomb Avenue Rehabilitation (Liberty Street to Burns Street)