This project will rehabilitate Golden Valley Road from Yorkshire Drive to North Virginia Street. The project will include a complete roadway reconstruction, replacement of sidewalk, curb, and gutter, correction of localized drainage deficiencies, and other incidentals necessary for the rehabilitation of the street.

LATEST NEWS
Final design is complete. Union Pacific Railroad (UPRR) is in progress of drafting agreement for railroad pad work to be completed by UPRR prior to road construction.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: September 2019 to October 2019
Final Design: November 2019 – April 2020
Construction: March 2021 – May 2021

 FINANCIAL INFORMATION
Total Project Estimate: $1,200,000
Funding Source: RTC Fuel Tax

 