PROJECT DETAILS
RTC Project No. 0212063

RTC Project Manager (PM)
Dale Keller, P.E.
(775) 335-1827
dkeller@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Lumos & Associates

Construction Contractor: to be determined

PROJECT DESCRIPTION
Rehabilitate Golden Valley Road from Yorkshire Drive to North Virginia Street. The project will include roadway reconstruction, sidewalk, curb and gutter replacement as necessary, correction of localized drainage deficiencies, and other incidentals necessary for the rehabilitation of the street.

LATEST NEWS
Final design is being coordinated with Union Pacific Railroad (UPRR).

 

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: September 2019 to October 2019
Final Design: November 2019 – April 2020
Construction: September 2020 – October 2020

 

FINANCIAL INFORMATION
Total Project Estimate: $1,500,000
Amount Approved: $1,500,000
Funding Source: RTC Fuel Tax

The Golden Valley Road Rehab Project is part of the approved 2020 Roadway Reconstruction Projects.

 

Post updated on: June 29, 2020