PROJECT DETAILS
RTC Project No. 232003

RTC Project Manager (PM)
Warren Call, P.E.
(775) 335-1881
wcall@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  Eastern Sierra Engineering

Construction Contractor: Sierra Nevada Construction, Inc.

PROJECT DESCRIPTION
This is a rehabilitation project of the Clean Water Way roadway from McCarran Boulevard to the Main Gate of the Truckee Meadows Water Reclamation Plant (TMWRP) (approximately 2.2 miles).

LATEST NEWS
The construction contract was awarded to Sierra Nevada Construction, Inc. on December 26, 2018.  Construction is scheduled to begin May 13 and be completed by July 8, 2019.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: April to June 2018
Final Design: June to November 2018
Construction Start: May 2019

FINANCIAL INFORMATION
Total Project Estimate: Between $1,500,000 and $2,500,000
Amount Approved: $2,700,000
Funding Source: RTC Fuel Tax

Post updated on:  April 30, 2019