PROJECT DETAILS
RTC Project No. 211005
RTC Project Manager (PM)
Maria Paz Fernandez, P.E.
(775) 335-1861
mpazfernandez@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax
Design Firm: Headway Transportation
Construction Contractor: To be determined
PROJECT DESCRIPTION
Design and construct a two-way cycle track on Center Street from Moran Street to 9th Street. Traffic Signals update/ modification/ replacement along the corridor. ADA improvements including pedestrian ramps.
Corrective pavement from First Street to Ninth Street.
Sidewalk replacement from Fifth Street to Ninth Street.
LATEST NEWS
The project is moving along with Design. 30% Plans are expected by the end of winter 2020 (March 2021).
SCHEDULE
Planning: April 2019
Environmental: N/A
Preliminary Design: Summer 2021
Final Design: Winter 2022
Construction: Summer 2023
FINANCIAL INFORMATION
Total Project Estimate: $13,000,000
Funding Source: RTC Fuel Tax
Post updated on: December 28, 2020