PROJECT DETAILS
RTC Project No. 211005

RTC Project Manager (PM)
Maria Paz Fernandez, P.E.
(775) 335-1861
mpazfernandez@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Headway Transportation

Construction Contractor: To be determined

PROJECT DESCRIPTION
Design and construct a two-way cycle track on Center Street from Moran Street to 9th Street. Traffic Signal update, modification, and replacement along the corridor.  ADA improvements including pedestrian ramps. Corrective pavement from First Street to Ninth Street, and sidewalk replacement from Fifth Street to Ninth Street.

LATEST NEWS
The project is under Design. Working on Interlocal Cooperative Agreement with City of Reno to finalize 30% Design (preliminary design).

Analysis of the implementation of directional protected cycle tracks through downtown Virginia Street was performed and the Draft Traffic Analysis was shared with City of Reno.  Other reasons and adjustments to be included and pending the Downtown Placemaking Study results.

SCHEDULE
Planning: April 2019
Environmental: N/A
Preliminary Design: Summer 2021
Final Design: Winter 2022
Construction: Summer 2023

FINANCIAL INFORMATION
Total Project Estimate: $11,080,000
Funding Source: RTC Fuel Tax

 

Post updated on: December 31, 2021