PROJECT DETAILS
RTC Project No. 211005

RTC Project Manager (PM)
Maria Paz Fernandez, P.E.
(775) 335-1861
mpazfernandez@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Headway Transportation

Construction Contractor: To be determined

PROJECT DESCRIPTION
Design and construct a two-way cycle track on Center Street from Cheney Street to 9th Street.

LATEST NEWS
Traffic Analysis of the corridor has been performed, the results are being presented to the City of Reno Councilmembers.

Amending the agreement to include design of the cycle track and adjust the project limits to Moran Street.

SCHEDULE
Planning: April 2019
Environmental: N/A
Preliminary Design: Summer 2021
Final Design: Winter 2022
Construction: Summer 2023

FINANCIAL INFORMATION
Total Project Estimate: $13,000,000
Funding Source: RTC Fuel Tax

 

Post updated on: August 31, 2020