PROJECT DETAILS
RTC Project No. 215004

RTC Project Manager (PM)
Scott Gibson, P.E.
(775) 335-1874
sgibson@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Wood Rogers

Construction Contractor: Sierra Nevada Construction

PROJECT DESCRIPTION
Anticipated improvements include the re-alignment of the Keystone and California intersection, lane reconfigurations, pavement section reconstruction, sidewalk curb, gutter, new PROWAG compliant pedestrian sidewalks, ramps, and other incidentals necessary for the final design of this facility. Limited right of way acquisition may be required to accommodate the new pedestrian ramp connections. Temporary construction easements will likely be required to accommodate the reconstruction of ADA facilities.

LATEST NEWS
The project is substantially complete. Please click here to view the Weekly Traffic Control Report for current closures and detour information.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: June 2018
Final Design: September 2018
Construction: June 2019

FINANCIAL INFORMATION
Total Project Estimate: $2,272,125
Amount Approved: $2,794,007
Funding Source: RTC Fuel Tax

Post updated on: January 27, 2020