PROJECT DETAILS
RTC Project No. 241005

RTC Project Manager (PM)
Judy Tortelli, P.E.
(775) 335-1824
jtortelli@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: CA Group, Inc.

Construction Contractor: N/A

PROJECT DESCRIPTION 
The program is a multi-year effort to upgrade existing bus stops to comply with state and federal requirements, including the Americans with Disabilities Act (ADA). The first phase of bus stop improvements located within public Right-of-Way (12 bus stops) is complete. The process of obtaining necessary easements for other locations is ongoing. The design consultant, CA Group submitted easement packages for 37 bus stop locations last year and acquisition work continues. Sixty percent (60%) Design was submitted for the final 90 bus stop locations. R/W for some bus stops has been acquired and we are moving forward with a Phase 2 Construction package that includes 30 bus stop locations.

LATEST NEWS
Design is complete and the Right-of-Way process is on-going. Phase 2 construction package will be issued for bidding in April 2021. Construction of 30 bus stops shall be taking place June to September 2021.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Complete
Final Design: Complete
Construction: Spring 2020

FINANCIAL INFORMATION
Total Project Estimate: $1,568,434
Funding Source: RTC Fuel Tax

 

Post updated on: March 31, 2021