Buck Drive Circulation Project will improve the existing and future traffic flow along Buck Drive between Lemmon Drive and North Hills Boulevard. Improvements include access management implementation, road widening with traffic signal at North Hills Boulevard.
LATEST NEWS
Kimley-Horn and Associates is the selected design firm to further evaluate and design the Buck Drive Circulation Project. RTC awarded the design agreement at the July Board meeting. The team is moving forward with preliminary design work. Fifty percent design plans are expected by first quarter of 2024.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring 2024
Final Design: Winter 2024
Construction: Spring 2025
FINANCIAL INFORMATION
Total Project Estimate: 4,000,000
Funding Source: RTC Fuel Tax