PROJECT DETAILS
RTC Project No. 212073

RTC Project Manager (PM)
Kimberly Diegle, P.E..
(775) 335-1844
kdiegle@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: Nichols Consulting Engineers

Construction Contractor: To be determined

PROJECT DESCRIPTION
Roadway rehabilitation or reconstruction of Arrowcreek Parkway from South Virginia Street to Rubblestone Drive. Construction work may include removal and replacement of the roadway structural section, sidewalk and curb and gutter replacement as necessary, reconstruction of existing curb ramps, traffic signal improvements, and other incidentals necessary for the rehabilitation and/or reconstruction of the street segment within the project limits.

LATEST NEWS
The design team is in progress to final design.

SCHEDULE
Planning: N/A
Environmental:
N/A
Preliminary Design:
Completed
Final Design:
Summer 2022 to Fall 2022
Construction:
Summer 2023

FINANCIAL INFORMATION
Total Project Estimate: $2,640,000
Funding Source:
RTC Fuel Tax


Post updated on: September 29, 2022