PROJECT DETAILS
RTC Project No. 212073

RTC Project Manager (PM)
Roy Flores, P.E., M.P.A.
(775) 335-1881
rflores@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm: To be determined

Construction Contractor: To be determined

PROJECT DESCRIPTION
The project includes rehabilitation and reconstruction of Arrowcreek Parkway from Rubblestone Drive to S. Virginia Street and ADA pedestrian ramp improvements

LATEST NEWS
Currently working on scope and fee with consultant.

SCHEDULE
Planning: N/A
Environmental:
N/A
Preliminary Design:
October 2021 to June 2022
Final Design:
June 2022 to January 2023
Construction:
Spring 2023

FINANCIAL INFORMATION
Total Project Estimate: $2,639,556
Funding Source:
RTC Fuel Tax

 

Post updated on: August 30, 2021