PROJECT DETAILS
RTC Project No. 0212080
RTC Project Manager (PM)
Jessica Dover
(775) 335-1831
jdover@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: To be determined
Construction Contractor: To be determined
PROJECT DESCRIPTION
Pavement Rehabilitation on Arrowcreek Parkway approximately 815′ west of Geyser Road to approximately 825′ northeast of Wedge Parkway and on Wedge Parkway from Mount Rose Highway to Whites Creek Lane.
LATEST NEWS
RTC is currently negotiating scope/fee with a consultant for engineering design and construction services. A contract for engineering services is anticipated to appear on the Fall 2023 RTC Board meeting agenda.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Spring/Summer 2024
Final Design: Summer 2025
Construction: Summer/Fall 2025
FINANCIAL INFORMATION
Total Project Estimate: 11,730,000
Funding Source: RTC Fuel Tax
Post updated on: August 25, 2023