PROJECT DETAILS
RTC Project No. 244008

RTC Project Manager (PM)
Scott Gibson, P.E.
(775) 335-1874
sgibson@rtcwashoe.com

RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax

Design Firm:  Lumos & Associates

Construction Contractor:  Sierra Nevada Construction

PROJECT DESCRIPTION
The program for this construction season includes corrective maintenance (asphalt concrete patching) of regional roads that require short-term maintenance measures to improve ride quality and durability until complete reconstruction can occur (approximately 3-5 years). This work is necessary because of the severe winter that has resulted in accelerated deterioration of those regional roads near the end of their life cycle.  The roads to be included in the project are located throughout the City of Reno, City of Sparks and Washoe County.

LATEST NEWS
Project is complete.

SCHEDULE
Planning: Complete February 2017
Environmental: N/A
Preliminary Design: Complete May 2017
Final Design:  Complete June 2017
Construction Start:  August 2017 to October 2018

FINANCIAL INFORMATION
Total Project Estimate:  $7,744,893
Amount Approved:  $7,744,893
Funding Source:  RTC Fuel Tax

Budget amount includes design and construction services.

Post updated on:  November 21, 2018