PROJECT DETAILS
RTC Project No. 232003
RTC Project Manager (PM)
Warren Call, P.E.
(775) 335-1881
wcall@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
(775) 348-0170 fax
Design Firm: Eastern Sierra Engineering
Construction Contractor: Sierra Nevada Construction, Inc.
PROJECT DESCRIPTION
This is a rehabilitation project of the Clean Water Way roadway from McCarran Boulevard to the Main Gate of the Truckee Meadows Water Reclamation Plant (TMWRP) (approximately 2.2 miles).
LATEST NEWS
Bids for project construction were received and opened on Friday, December 14, 2018. The construction contract was awarded to Sierra Nevada Construction, Inc. on December 26, 2018. Construction is slated for Spring 2019.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: April to June 2018
Final Design: June to November 2018
Construction Start: Estimated start date April 2019
FINANCIAL INFORMATION
Total Project Estimate: Between $1,500,000 and $2,500,000
Amount Approved: $2,700,000
Funding Source: RTC Fuel Tax
Post updated on: January 25, 2019