PROJECT DETAILS
RTC Project No. 0532015

RTC Project Manager (PM)
Garrett Rodgers, P.E.
(775) 332-2139
grodgers@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Design Firm: Kimley-Horn & Associates

Construction Contractor: Sierra Nevada Construction

PROJECT DESCRIPTION
This project includes:
Package A: new roundabout at intersection of 4th Street/Woodland Avenue along with geometric changes to 4th Street at Mesa Park Road.
Package B: extend southbound left turn at the intersection of South Virginia Street and Kietzke Lane.

Please visit 4th Street and Woodland Avenue Roundabout  for more information.

LATEST NEWS
Construction of a new roundabout at the intersection of Woodland Avenue and W. 4th Street has resumed.  Two-way traffic control on W. 4th Street and Woodland Avenue is in place and will be maintained approximately through end of May.  Mesa Park Road from W. 4th Street to 500 feet north is closed through May during construction of a retaining wall below Mesa Park Road.

The project is located in the City of Reno. 4th Street is a Nevada Department of Transportation (NDOT) maintained roadway.

The project is anticipated to be complete by the end of August 2023.

SCHEDULE
Planning: Complete
Environmental: N/A
Preliminary Design: Winter 2021
Final Design: February 2022
Construction: Summer 2023

FINANCIAL INFORMATION
Total Project Estimate:
$ 5,279,124
Funding Source: Regional Road Impact Fee (RRIF)


Post updated on: May 31, 2023

4th Street and Woodland Avenue Roundabout Project Map